In the German district of Donau-Ries, the Danube River forms a natural barrier, making bridges essential to the regional infrastructure. Building or replacing these bridges presents major logistical and engineering challenges, particularly when disruption to shipping and river traffic needs to be kept to a minimum.
For complex marine construction and bridge installation projects, Baars provides flexible and practical solutions using modular floating equipment. This was recently demonstrated during the installation of a new 107.5-metre-long, 900-ton steel bridge at Marxheim in southern Germany.
Precision on the Danube: floating a 900-ton bridge into position
The new steel arch bridge was constructed alongside the river before being moved across the Danube on a specially configured floating pontoon platform.
This installation method made it possible to move the complete bridge structure across the river in a controlled manner, while minimising disruption to the surrounding infrastructure and river traffic.
During the operation, the 900-ton steel bridge was moved centimetre by centimetre across the Danube, supported by a Baars modular pontoon configuration.
The pontoon system was engineered to provide the required buoyancy, load distribution and stability throughout the operation. This gave the contractor a stable floating foundation from which the exceptionally heavy bridge structure could be manoeuvred accurately towards its final position.
Specialised transport platforms on shore moved the bridge forwards in precise coordination with the pontoon platform on the water.
Modular pontoons for heavy bridge installation
For this demanding bridge installation project in Germany, Baars supplied 9.5 ft modular pontoons.
One of the main advantages of the Baars modular pontoon system is its flexibility. Individual pontoon sections can be combined into a platform specifically configured for the dimensions, loads and operational requirements of a project. For the Marxheim bridge installation, this allowed Baars to provide the required floating capacity without supplying unnecessary equipment.
Due to the exceptional weight of the steel bridge, heavy-duty seagoing modular pontoons were selected for the operation. These pontoons provided the load capacity and robust floating foundation required for moving the 900-ton structure across the Danube.The complete pontoon system, including its supporting structures, had a total weight of approximately 88 tons.
The result was a stable and reliable floating platform for heavy-load bridge installation, supporting both the movement of the bridge and the personnel and equipment involved in the operation.
Complete pontoon transport, assembly and demobilisation
Supplying the modular pontoons was only one part of the Baars solution.
Baars also organised the road transport of the pontoon equipment to the project site in Germany. After arrival, experienced Baars engineers assembled the modular pontoon system on location and prepared the platform for the bridge installation operation. This one-stop-shop approach significantly simplifies project logistics for contractors. Instead of coordinating separate suppliers for pontoon rental, transport, assembly and demobilisation, these services can be managed through one specialist partner.
After completion of the bridge installation, Baars also takes care of dismantling the pontoon configuration and organising the return transport.This reduces coordination, saves valuable project time and allows the contractor to concentrate on the core construction activities.
Modular pontoon solutions for infrastructure projects worldwide
The Marxheim bridge project demonstrates the versatility of Baars modular pontoons for complex infrastructure and marine construction projects. From bridge installation and heavy-load operations to temporary working platforms and specialised marine construction, modular pontoons can be configured around the specific requirements of each project.
Inventive, flexible and well-engineered. Our creativity is your solution!
Are you planning a bridge installation, heavy-load operation or marine construction project and looking for the right floating solution?
Contact Baars to discuss your project requirements. Our team can help determine the most suitable modular pontoon configuration, transport solution and on-site support for your operation.
Want to see how the Marxheim bridge was installed? Read the full report by BR24 about the operation on the Danube. Read more for the full report by BR24 .